Assignment: Finance Help Prob 1-4 Paper

Assignment: Finance Help Prob 1-4 Paper

Assignment: Finance Help Prob 1-4 Paper

Permalink: https://ulcius.com/assignment-finan…p-prob-1-4-paper/ ‎

value:
3.00 points

 

Problem 6-1

An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 18 minutes. The line will operate for 450 minutes per day.

 

a. What are the minimum and maximum cycle times? (Round your answers to 1 decimal place.)

 

  Minimum cycle time
II
III
IV

 

e. Compute the percentage of idle time for the assignment in part d. Use the actual bottleneck cycle time in your calculation. (Round your answer to 1 decimal place. Omit the “%” sign in your response.)

 

  Percentage of idle time
II
III
IV
V

 

e. Calculate the percentage idle time for the line using the 50 second cycle time. (Round your answer to 1 decimal place. Omit the “%” sign in your response.)

 

  Percentage of idle time
II
III
IV

 

b. In order of greatest positional weight.

 

Work Station Tasks
I
II
III
IV

 

c. What is the efficiency? (Round your answer to 2 decimal places. Omit the “%” sign in your response. )

 

 

   Efficiency [removed]  %

Problem 6-1

An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 18 minutes. The line will operate for 450 minutes per day.

 

a. What are the minimum and maximum cycle times? (Round your answers to 1 decimal place.)

 

  Minimum cycle time   minutes
  Maximum cycle time    minutes

 

b. What range of daily output is theoretically possible for the line? (Round your answers to 1 decimal place. Enter the smaller value in the first box and the larger value in the second box.)

 

  Range of output   to    units/day

 

c. What is the minimum number of workstations needed if the maximum output rate is to be sought?(Round up your answer to the next whole number.)

 

  Minimum number of workstations

 

d. What cycle time will provide an output rate of 125 units per day? (Round your answer to 1 decimal place.)

 

  Cycle time   min/cycle

 

e. What output potential will result if the cycle time is (1) 9 minutes? (2) 15 minutes?

 

  Cycle Time   Potential Output
(1)  units
(2)  units

2.

value: 3.00 points

 

Problem 6-5

As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as follows:

 

Task Duration (minutes) Immediate Predecessor
a 0.2
b 0.4 a
c 0.2 b
d 0.4
e 1.2 d
f 1.2 c
g 1.0 e, f

 

Do each of the following:

 

b. Determine the minimum cycle time, the maximum cycle time, and the calculated cycle time.(Round your answers to 1 decimal place.)

 

  The minimum cycle time  minutes per unit
  The maximum cycle time  minutes per unit
  Calculated cycle time  minutes per unit